ii.Construction
3-14 may 2010
My first day in the construction was on 3/5 till 14/5.i met the head of the construction unit EN.mukhlis bin zulkipli ,,I have a bit talk with him as I have an idea about the distribution and the power planet from the maintenance department.
He explained to me in brief the normal mission of the construction unit which is:-
Firstly the unit will handle the project after the design/plans are approved.
Secondly the unit is responsible to make sure that all civil infrastructure (manholes, ducts, and substation) and electrical equipments (cables, transformer, switchgears and feeder pillar) are being installed following the correct procedures.
Thirdly the unit are responsible to do a switchgear shutdown, identified the cable to be cut and joined before issuing PTW (permit to work) to contractor.
Then mr mukhlis bin zulkipli got busy with a visitors so that he pass me to the leaders of the construction team mr Termizi and mr,azizul to continue what he had started and earn more info by taking me to some new project which are still under procedure.
Mr Termizi describe how risky and danger are them function because if there is any wrong it cause power supply outage to the customer and it may also cause bad incident for the contractor, for the sake of the power supply incident there are a mandatory steps that the construction unit must follow it which are:
1- Identify substations and normal off point (NOP) in the loop that related with the project to ensure continuous power supply for correlated customers.
2- Authorized person must issue permit to work before the contractors start working and cancel it after the job is completely done.
3- The competent person and the authorized person are taking the taking the full responsibility because there are the only persons who are doing the switching and normalization of the supply system.
During the 2 weeks in construction unit I have learn several things which is:
1- Loop in loop out (LILO) CABLE.
2- Adjusting the underground cable.
3- Fusion connection
4- Cutting ,Joining ,changing the Underground cable
5- Tests done on the cable.
Loop in loop out (LILO) CABLE.
Cable (LILO) is a common project in new industrial park. The main objective is to connect new cables with the existing one and make a new joint. And the procedure is:
Shutdown the power supply: - this procedure is done on the cable involved to make sure no current discharge that could harm the worker.
Normal off point: - is move to a new point in order to maintain the power supply of current customer.
The cables are jointed together and loop into the system.
Adjusting the underground cable :
Ø Distribution cable to the customer
Ø The cable is step down from the substation with 11 KV 415V then its spreads into (MSB) mother Switch Board of each host/house.
Ø Mother Switch Board (MSB)
· Deliver 240 to the plug port
· Contain fuse ; avoid damage to the cable plus its more safety and costing less money.


Ø Steps to install a distribution and the feedback cable :
· Redraw the underground cable
· Plan and Predict for all possiblities in the future.
· Interconnect and install the cable.
Ø Advantage of feed back box distribution cable:
· Easy to trouble shoot
· Maintain service to customer all the time.
· Minimize the danger for technician and easy to connect.

Ø An example of cable redraw and how the feedback Box are working and helping to feed back the supply

· feed back box always on OFF .
· if the supply is OFF from the distribution box the Feed Back box automatically will turn ON
· if there is a maintenance or break down between point 1 and point 2
¾ Firstly they turn OFF the distribution and the feed back as well the
¾ Secondly they will cut OFF the supply at point 1 and 2 .
Then they will TURN ON the both Boxes and the supply will passing through the circuit except the line which is between Point 1 and 2.
Fusion connection

Ø T
here is 2 types of fusion :
Cut-Out fused :- 240 v
Its 3 phase and single phase connecting to the switch board.
J-Slotted fused
Ø Steps of connecting the fuse and the 3-phase rotation device :
· Fuse :
¾ Release the black screw till the end.
¾ Put the fuse between the holder.
¾ Balance and close the black screw.
· F
· 3-phase rotation device :-
¾ The device contain 3 cable (Red, Yellow, Blue)
¾ Connect each color to the right position in feeder pillar .
¾ Check the devices if its rotate in clock wise .it means the connection is correct ,,if moves in comer clock wise it means the connection is reversal.
Cutting ,Joining ,changing the Underground cable :
Ø TNB is supplying electricity to consumer in putrajaya and cyperjaya region by underground cable .
Ø The procedure of cutting ,changing or joining are :-
¾ Use the CABLE IDENTIFICATION SYSTEM
¾ Take out the water from underground by the blower.
¾ Use the Hydrolic cutter to cut a big width cable from far distance for safety purposes.


Ø
Steps of using the cable identification system:-
.JPG)
¾ Connect the transmitter to the feeder.
¾ Use the receiver and tong to indicate the flow of current to know which cable
has no current flow to cut it.
Steps of using Hydraulic cutter:-

¾ after indicating the cable which is out of the current flow.
¾ Evacuate the worker and the technician from underground.
¾ Press frequently the hydraulic cutter and look to the meter indicator the indicator will arise to current point then get back to the zero.
¾ Go down to the underground ,,check the cable by the following tests which I
illustrate it down ,,then join it back.



Tests done in the cable.
1. Phasing Resistance Test.
Ø To test and identify the phase of underground cables.
Ø Also to make sure the phase of underground cables is in correct sequence.
2. Continuity test
Equipment: mugger
Objective: to determine if a complete electrical circuit can be established between two points. The circuit under test is completely de-energized prior to connecting the apparatus.